A brand new 2 storey 66 bedroom care home in Ryhope, Sunderland.

PROJECT UPDATE:

  • Site clearance works have been undertaken, including demolition of former C of E school and removal of playgrounds, walls and levels have been reduced.
  • All pre-development planning conditions have now been discharged.
  • New drain diversion has been completed.
  • Works commenced early November 2018 with drainage diversions and substructure foundations.
  • Piled foundations have been completed.
  • PCC ground floor should be completed within the next few weeks.
  • Tower crane has now been erected for the installation for steelwork and blockwork.

 

 

 

 

 

 

 

 

 

 

March 2019